| Project Milestone | Description (Days from Appointed Date) | Physical Progress (%) | Schedule Date | Revised Schedule Date as per approved EOT | Achieved Date |
| Milestone I | 180th Day | 20% | 26/9/2022 | 20/12/2022 | 26/9/2022 |
| Milestone II | 365th Day | 35% | 30/3/2023 | 4/4/2023 | 30/3/2023 |
| Milestone III | 550th Day | 75% | 1/10/2023 | 30/11/2024 | 30/11/2024 |
| Scheduled Completion | 730th Day | 100% | 29/3/2024 | 14/4/2026 | Under progress |
| S.No. | Items | Scope (in Km) | Completed (in Km) | Balance (in Km) |
| 1 | C&G (Clearing & Grubbing) | 56.944 | 56.944 | 0.000 |
| 2 | Embankment Top | 56.944 | 52.962 | 3.982 |
| 3 | Subgrade Top | 56.944 | 52.962 | 3.982 |
| 4 | GSB (Granular Sub-Base) | 56.944 | 52.472 | 4.472 |
| 5 | AIL | 56.944 | 49.560 | 7.384 |
| 6 | DBM (Dense Bituminous Macadam) | 56.944 | 49.512 | 7.432 |
| 7 | BC (Bituminous Concrete/Wearing Course) | 56.944 | 49.070 | 7.874 |
| S.No. | Items | Total No. of Structures | Status | Balance |
| 1 | Major Bridge | 3 | 3 | 0 |
| 2 | Minor Bridge | 13 | 12.50 | 0.50 |
| 3 | Culverts | 115 | 114 | 1 |
| 4 | Viaduct | 12 | 10 | 2 |
| 5 | VUPs | 2 | 2 | 0 |
| 6 | VOPs | 1 | 0 | 1 |
| 7 | LVUPs | 3 | 3 | 0 |
| 8 | AUPs | 0 | 0 | 0 |
| 9 | Monket Canopies | 0 | 0 | 0 |
| 10 | Interchanges | 1 | 1 | 0 |
| 11 | Way Side Amenities | 2 | 0 | 2 |
| 12 | ROB | 0 | 0 | 0 |