Project Salient Features
Name of the Project Development of Six Lane Aluru-Jakkuva section of NH-130-CD Road from km 365.033 to km 396.800 under Raipur – Visakhapatnam Economic Corridor in the State of Andhra Pradesh on Hybrid Annuity Mode. [Package-1(AP)]
Description of the Project Raipur – Visakhapatnam Economic Corridor
Authority NHAI
Scheme BM-1
Mode of Implementation HAM
Name of NH NH-130-CD
Name of Concessionaire M/s H. G. Raipur Visakhapatnam AP-1 Private Limited
Date of LOA 30/7/2021
Date of signing of Agreement 14/10/2021
Appointed Date 31/3/2022
Scheduled completion date 30/3/2024
Likely completion date 14/4/2026
Construction Period 730 Days
O&M Period 15 Years from COD
Length of Project 31.767 (6 Lane Length)
Bid Project cost Rs. 1060.11 Cr.
Sanctioned cost Rs. 922.5 Cr.
Total Capital Cost Rs. 1216.12
Independent Engineer M/s ISAN Corporation in JV with Chaitanya Projects Consultants Private Limited
Deployment of IE 01.02.2022
Contract Amount of IE Rs.5.21 Cr.
Scheduled Completion of IE Tenure 31.01.2026
Safety Consultant Road Link Consultancy Services
Date of deployment 11.07.2022
Contract Amount Rs.88.90 Lakhs
Tenure Upto Till Completion of the Project
Physical Progress (Till Date) 90.30%
Financial Progress 91.20%
Expenditure (payment to concessionaire) Rs.519.45 Cr.