| Name of the Project | Development of Six Lane Aluru-Jakkuva section of NH-130-CD Road from km 365.033 to km 396.800 under Raipur – Visakhapatnam Economic Corridor in the State of Andhra Pradesh on Hybrid Annuity Mode. [Package-1(AP)] |
| Description of the Project | Raipur – Visakhapatnam Economic Corridor |
| Authority | NHAI |
| Scheme | BM-1 |
| Mode of Implementation | HAM |
| Name of NH | NH-130-CD |
| Name of Concessionaire | M/s H. G. Raipur Visakhapatnam AP-1 Private Limited |
| Date of LOA | 30/7/2021 |
| Date of signing of Agreement | 14/10/2021 |
| Appointed Date | 31/3/2022 |
| Scheduled completion date | 30/3/2024 |
| Likely completion date | 14/4/2026 |
| Construction Period | 730 Days |
| O&M Period | 15 Years from COD |
| Length of Project | 31.767 (6 Lane Length) |
| Bid Project cost | Rs. 1060.11 Cr. |
| Sanctioned cost | Rs. 922.5 Cr. |
| Total Capital Cost | Rs. 1216.12 |
| Independent Engineer | M/s ISAN Corporation in JV with Chaitanya Projects Consultants Private Limited |
| Deployment of IE | 01.02.2022 |
| Contract Amount of IE | Rs.5.21 Cr. |
| Scheduled Completion of IE Tenure | 31.01.2026 |
| Safety Consultant | Road Link Consultancy Services |
| Date of deployment | 11.07.2022 |
| Contract Amount | Rs.88.90 Lakhs |
| Tenure Upto | Till Completion of the Project |
| Physical Progress (Till Date) | 90.30% |
| Financial Progress | 91.20% |
| Expenditure (payment to concessionaire) | Rs.519.45 Cr. |